We could almost hear the gasp of relief from the form as it is released of the duty of supporting over ten tons of stone for the last two weeks. 



The form was lowered several inches by chain sawing and then knocking out a few of the cedar logs in the crib that was supporting it. Two of us were then able to slide the form out.